Transurban brought this project to government, it selected the builders, it identified the presence of PFAS and then signed a contract to deliver the project they need to finally settle this dispute with their builders and get on with the project.
Transurban…
West Gate Tunnel budget blows out by $3.3 billion, Transurban reveals – The Age